January-February 2005

  • 1
  • 2

DG Coming to the Grid's Rescue

California study totals up the value of onsite power to electric companies.

Article Tools

Create a Link to this Article

By David Engle

Comments

"Distributed generation hurts utilities!" cry electric company engineers who believe that haphazardly sited engines threaten grid safety. The result: Prohibitively high connection charges are imposed.

"DG really helps utilities," say others, including rate-setting commissioners in California and New York in 2004, the US Department of Energy, assorted consumer advocacy groups, and the DG industry.

Which view is right?
Perhaps there's a better question: Which side can back up its claim with compelling, reliable facts? Both sides have struggled with the complexities of quantifying potential benefits or harm and yielding solid, credible data. Both sides offer sweeping but "basically unsubstantiated" claims, observes Peter Evans, CEO of New Power Technologies (NPT) in Los Altos Hills, CA. NPT develops management solutions for the power industry. Missing from the debate, however, were methodologies for serious DG impact studies, resource optimization analysis, and comparative technology assessments. Until recently, Evans points out, no one had been able to solve puzzles like right-sizing DG resources (from the grid's standpoint), where resources should go, or what actual dollar value they would bring to the utility company.

All of this has now radically changed. During 2003–2004, NPT led a research team that produced a landmark study in nearby Silicon Valley showing these critical issues can indeed be addressed reliably—probably for the first time ever. Along with Evans and NPT, 10 other co-participants included Optimal Technologies Inc. of Benicia, CA, which provided principal optimization technology and services for the study; Cupertino Electric, which assisted in developing the system model; the Silicon Valley Manufacturing Group (SVMG); and consultancies Rita Norton & Associates, William M. Stephenson, and Roy Skinner. Funding for the study, and strong state-level encouragement, came from the Public Interest Energy Research (PIER) program within the California Energy Commission (CEC), both of which have long been major sponsors and benefactors of DG-related research and development (R&D).

To serve as a test-case system for undertaking this DG-on-grid analysis, Evans and the SVMG solicited the participation of Silicon Valley Power (SVP), a municipal network of 850 buses serving the city of Santa Clara. SVP's transmission backbones include two 115-kV main feeds, a 60-kV transmission system, and 48 or more distribution feeders of 12 kV, lightly loaded off of about 422 customer locations. That works out, Evans notes, to nearly 1,000 line segments with 106 switchable branches connecting them, 101 switchable capacitors, and six onsite generators with megawatt and megavar capability already in the mix.

What the Study Found
After several months of studying grid optimization with DG sets, Evans issued his report to the CEC, from which the following summary and discussion is adapted. In essence, researchers learned that, indeed, small generators sited strategically on the distribution system would yield potentially tremendous improvements to system efficiency. Moreover, further gains and benefits would accrue to the interconnected transmission system. DG's value to both would be realized not only by the additional reserve power provided, but, even more so, from DG's ability to ease power delivery across hundreds of strained, occasionally redundant, energy-sapping distribution lines.

In any grid system, hundreds and even thousands of kilowatts are squandered in the task of moving amps across needlessly long distances squeezing through local bottlenecks and loop flows. The results: weaker voltage profiles, voltage instability, and poor power quality. Properly positioned DG can greatly reduce system congestion and curtail waste of this sort. The potential savings should readily cost-justify, and subsidize, many cogen investments.

For example, as the report notes, unstable voltage must often be boosted to maintain a sufficient minimum. But if more stable distribution system voltages could be achieved—a potential byproduct of many DG projects—it would reduce the need for wasteful over-amping.

Moreover, researchers found that system voltage stability is closely linked to optimal distribution of the system's reactive power resources, or var. What impact does DG have here? The question can now be answered using breakthrough software from Optimal Technologies called AEMPFAST (pronounced "aim-fast"). Using this tool, Evans' team evaluated and quantified both active (kilowatt and megawatt) and reactive (var and MVar) power flows and events that could lead to cost-justifiable DG sites. Evans' conclusion: "There's a lot more you can do with reactive power," he says, "from a distributed generator, toward providing system benefits."

Sharing Benefits With Adopters
What this insight also suggests is that a prospective DG adopter whose generator might provide such benefits should probably receive some kind of compensation or inducement. Optimal Technologies CEO Roland Schoettle suggests that these might come, for example, "through appropriately structured ancillary power markets, where these benefits are quantified and ranked as alternatives." DG resource optimization on a grid, he adds, "would make certain that all the lowest cost-benefit alternatives would be known and ranked" in utility management decisions, "not just the traditionally obvious ones using standard utility methods."

Schoettle's AEMPFAST also assessed SVP customer demand response measures designed for reducing system peak demand. AEMPFAST's study established that demand response, wherever onsite power is applied, has greater system benefits in certain locations within a distribution system than in others. Hence, the widely asserted "safety risk" to grid security, so often leveled at DG projects, is just the opposite of the truth: Risks are actually lowered by the presence of DG, AEMPFAST learned. Again, says Evans, utilities "would be acting in their self-interest" by giving out carefully targeted incentives to DG adopters, especially where the result is peak-demand reduction.

Evans says other kinds of grid benefits accrue, including "all network-related, avoided, or deferred additions"; improved supply-demand margins; reduced dependence on electricity spot markets; deferred costs; reduced fuel costs; lowered emissions and related costs; and easier integration of future customer-driven onsite power projects into the grid. Lastly, with customer-owned DG in the right places, low-voltage buses can sometimes be eliminated outright.

All in all, then, grids can be "tuned up" with DG networks and made more efficient, says Evans, "by minimizing real power losses and reactive power consumption."

To illustrate, Evans notes that on a 60-kV main feeder (such as at SVP) at a transmission-to-distribution stepdown point where the feeder connects to a 12-kV line (and that, in turn, to low-voltage buses), a system will typically show voltage variability. Although this isn't a problem from an engineering standpoint, he says, "It's waste, and it presents an opportunity for optimization." By carefully measuring these and assorted other losses, then determining and ranking how they'd be reduced by a customer-installed generator nearby, a grid-improvement value results. And again, in incentive terms, a portion should be rebated to the adopter.

Another example: A customer installing a 150-kW combined heat and power system might allow for eliminating a nearby low-voltage bus, or might flatten the overall voltage profile on that 12-kV line. The current would become more consistent. This would reduce wastage, thereby saving the utility something in the low four-figures each year.

DG is but one of several solutions to be applied systematically in a well-optimized grid. Others include, Evans says, "More automated remote switching, changeable topology, controllable capacitors, distribution automation, sophisticated demand-response programs," and assorted others. "That's the direction this will head to. Distributed generation is maybe the most important piece of that, but it is not the only piece."

Siting for Maximum Benefit
Back, now, to the question of precisely where generators should go, and their potential dollar value. Here AEMPFAST's tools for DG-on-grid analysis are able to integrate complex interrelated functions: system security, voltage profiles, reliability, congestion, minimum loss, minimum generation cost, minimum emission, minimum maintenance, locational marginal costs, congestion mitigation, and sophisticated asset optimization. Schoettle adds that his product "is not based on the mathematical engines now prevalent," and so "does not suffer from their limitations." AEMPFAST analyzes a grid's physical condition, virtually in real time (or with only a few seconds' lag) and seeks to give system engineers best-possible resource deployment choices. In so doing, it also ranks every component as to its net benefit, and to meeting the optimization objectives. These, says Schoettle, "can be multiple and varied, and can include both engineering and business objectives." Even very fine detail and micro-analysis is possible. Evans notes that in the SVP study, "We could actually go down to line segment–by–line segment" to detect waste and to quantify savings opportunities, as well as doing the assessment device by device. Schoettle also notes that customer onsite power projects can often accomplish distribution savings and efficiencies "if located and sized optimally" to solve problems, "as well as serving the customer cost-effectively."

With these win-win criteria in mind, then, Evan's team launched the DG siting analysis. He assumed non-exporting generators that were switchable and dispatchable.

In the first what-if scenario, the DGs were limited to the light load on the feeder, meaning they could add only a maximum of 15% of the feeder power (meeting the cap under California's Rule 21 limit for expedited interconnections).

Given this input, then, AEMPFAST identified 382 customer sites where DG would help the grid significantly. The aggregated total in new generation would be optimize at 13.6 MW; that's about 36 kW per generator, totaling 3.4% of peak load.

A second what-if scenario optimized Silicon Valley Power's light feeders. California grid connection rules are more liberal here, permitting up to 60% of the adjacent load to come from non-exporting DGs. On these, Evan's group found 346 prime customer sites for onsite power, totaling 38 MW (9.7% of total peak load and about 110 kW per generator).

Advertisement

In AEMPFAST's number-crunching came one surprising twist: The data showed that relatively small DGs, averaging much less than 150 kW, can carry almost disproportionate impact. In fact, one of the highest-prioritized potential DG sites that AEMPFAST flagged called for a mere 7 kW to support one customer's 14-kW load. Nevertheless, this particular locale was so critical to the grid, Evans explains, that "adding capacity there would benefit the entire system."

For multiple reasons, small-footprint power projects are generally easier to position near the feeder loads than are megawatt-size ones. Likewise, smaller generators can more readily be optimally sized to match loads. "The sweet spot here," Evans says, "tends to fall somewhere between 100 and 300 kilowatts." In this size range, scores of cogen installations turned out to be very cost-effective for customers, especially when the analysis could assume low or subsidized up-front costs. Next Page >

  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!