January-February 2007

  • 1
  • 2

Twenty-Two Floors of Energy Efficiency

An innovative office building takes advantage of the "spark spread"—the difference between the price of natural gas and the cost of electricity.

Article Tools

Create a Link to this Article

By George Leposky

Comments


Attracted by the lithium bromide, the water vapor then migrates from the evaporator into the absorber. There its condensation and absorption into the lithium bromide releases heat, which the cooling-water loop carries away.

En route back to the generator vessel to repeat the process, the diluted lithium bromide passes through a solution heat exchanger that transfers heat from the concentrated lithium bromide to the diluted solution. The solution heat exchanger helps to remove heat from the absorber and decreases the amount of heat needed to boil the diluted solution.

All of this takes place in a vacuum to make the lithium bromide and water solution more dense, so its propensity to absorb water vapor increases. In an evacuated chamber, the evaporation effect is enhanced and occurs at a lower temperature.

Ammonia is used often as an absorbent in industrial settings such as the food-processing industry, because it allows evaporation to occur at temperatures down to 0.0°F., but ammonia is a very toxic gas. Its use in a commercial application such as 550 North Brand would require compliance with stringent and costly safety requirements. The lithium bromide absorbent limits chilling of the water to 42°F. “Water freezes at 32 degrees Fahrenheit, and you need a little margin,” Lenel says. “Crystallization can be going on before the water freezes, and you don’t want any ice buildup.”

The generator exhaust goes through a heat-recovery system, supercritical silencers, and an exhaust line that rises up outside the building.

System Integration
The flow rate in the chilled-water line from the absorption chiller is 651 gallons per minute. This line runs parallel to the chilled-water lines from the building’s two existing 350-ton mechanical chillers.

Integrating the absorption chiller into the existing air-conditioning system was a challenge, Lenel says. The building has a sophisticated Siemens Apogee energy-management system with Insight software that controls how many chillers are on at what rate, how much the chilled-water control valve for each air-handling unit is open, and how the chilled-water pumps operate.

“The Siemens system gives us a set point to run the chilled-water pump,” Lenel says. “We use the absorption chiller as the baseload chiller—the first one in service, if the generators are running and it’s available. Then the existing two mechanical chillers are added according to the load.”

Acoustic Design
Because 550 North Brand is in a mixed commercial-residential neighborhood, the cogeneration system had to meet stringent acoustic-design requirements. “It’s whisper-quiet,” Lenel says. “When you’re outside the building, you don’t know whether it’s running or not. You don’t hear it. Inside, you would hear it if you were in the engine room. Right next to the engine you need hearing protection. It’s over 100 dB. Outside we easily fulfill the Occupational Safety & Health Administration requirement for 65 dB in nonindustrial areas.

“We chose a premium cooling tower with very good sound reduction, and built a masonry block generator room with appropriate acoustical sound traps—baffles of a specific shape, with pinholes in them. You can look right through, but sound doesn’t make it through too well.

“We draw a lot of air through the generator room to keep the units cool. There’s an oversized fan to carry exhaust out of the engine room, but it’s operated by a variable frequency drive at about 25% of its nominal flow rate, so low that you don’t hear it, and it’s on only when the cogeneration system is operating. The building already had two big exhaust fans for the parking garage, and that’s the only noise you hear.”

The generator exhaust goes through a heat-recovery system, supercritical silencers, and an exhaust line that rises up outside the building and overhead to the atmosphere. The dampening for those silencers is such that one can hear only the sound of moving air, but not the engine’s pulsations.

An Elderly Technology
Absorption chillers aren’t new. They first appeared in the early 20th century, and they were in great demand up to the 1960s, especially in cities that had downtown steam networks. “San Francisco has a central power plant that distributes steam through the city, and people installed absorption chillers to use that steam,” Lenel says. “That was a good way to go when coal was cheap, but when energy costs started to rise, the COP [coefficient of performance—the ratio of energy consumed to the cooling effect delivered] was lousy.

“The COP of a single-stage absorption chiller is about 0.7. If you put in one million Btus of hot water, you get only 700,000 Btus of chilling capacity. A modern electrically driven mechanical chiller has a COP of between 4.5 and 7.5, and now most are at the higher end of that range, so for every kilowatt of electrical energy, you get 7 kilowatts of cooling energy.”

Lenel explains that cogeneration in the United States is a byproduct of demand for electricity. “Typically, in Europe, it’s the other way around,” he says. “You generate electricity to create load for your thermal demand, but electric tariffs here offer no incentive or ability to export power, so everything is done based on electric demand and thermal output is a byproduct—a bonus.”

Not Primary Power
The generators at 550 North Brand weren’t sized to serve as a primary power plant for the building. If that had been the intent, the system would require a third or even a fourth generator to provide a cushion for scheduled equipment maintenance and unscheduled breakdowns.

The two generators can produce a total of 750 kW, representing about two-thirds of the building’s typical load at 95% occupancy. Because the interconnection agreement with GWP prohibits the building from exporting power, the cogeneration system’s controls are set to accept at least 50 kW from GWP at all times.

“The generators were sized to limit the peak grid demand of the building to 500 kW,” Lenel says. “Guaranteeing that limit makes the building eligible for a more favorable electricity pricing pattern.”

The dispatch routine for the generators is based on time of day or load demand, or a combination of both. It’s controlled by the building’s energy-management system, based on computer programs Northern Power developed to model the savings and dispatch the generators to their best economic advantage.

The gensets automatically share lead duties, according to which one has run the most hours. If necessary, an operator can override the automatic selection. The generators typically run during weekdays when demand is at its peak, though they could run at night if sufficient load exists.

Because service technicians from Northern Power’s southern California service office participated in installation and commissioning of the cogeneration system, they already were familiar with it when they assumed responsibility for its operation and maintenance. “We’re particularly proud that we can offer a service package,” Lenel says. “Before we had a service capability, we would turn a completed installation over to a maintenance company, which sometimes would question whether the control system was working properly and should be covered as a maintenance item. With our own service arm, we’re all on the same team.”

Refining the System
Within months after the cogeneration system entered service, Northern Power began modifying it to serve as a standby power system. This entailed control modifications and installation of a standby power circuit—a separate 600-amp, 480-volt, three-phase distribution feeder—that runs to the electric rooms up to the 17th floor.

“If GWP has an outage, the generators will provide an alternate power source to customers who pay for that privilege,” Lenel says. “Tenants coming in are attracted by the possibility of standby power on the floors that have it. Utility equipment occupies much of the 18th through 21st floors, but we could have extended it a few more feet up into the building had the space or desire been available up there.”

Another possibility is using cogeneration to heat the building. At present, electrical coils in the air handlers provide heat. Those would have to be replaced with hot water coils, which would require a hot-water distribution system.

Munselle says such a distribution system already exists. “We built a spare loop in the building in case we had tenants who wanted chilled water off the plant, but that never happened. The loop is there, virgin and unused, with taps on every floor. Whatever hot water isn’t being used in the absorber can be sent up into those coils. We’ll place the coils into the hot side of the HVAC system, then run the hot water through the loop and blow the fans over the hot water.

“During the winter, I could simultaneously energize the chilled-water loop to keep computer rooms in the building cool, while the hot-water loop supplements office heating with extra heat from the hot water that otherwise would not be used.”

Implementing that concept is a year or two away, Munselle says. He estimates that it will pay for itself within five years.

Advertisement

At present, the generators have a gross electrical efficiency of just 32.2% based on lower heating volume (LHV), without taking the cogeneration into account. That means only 32.2% of the energy in the natural gas is being used to generate electricity.

With the absorption chiller in operation, gross overall efficiency is 68% based on LHV, which means 68% of the energy in the gas is being used as electrical power or chilling capacity. “That’s fairly low,” Lenel says. “The absorption chiller is not a very efficient machine. A lot of heat goes back to the cooling tower. If you used that wasted heat to heat the building, you would raise the cogeneration system’s gross overall efficiency into the 80% to 90% range.”

Author's Bio: George Leposky is a science and technology writer based in Miami, FL.

  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!