July-August 2007

Extreme Makeover: Health Care Edition

An award-winning hospital upgrades cooling, laundry, and waste disposal to the tune of millions in energy savings.

Article Tools

Create a Link to this Article

By Don Talend

Comments

Modernizing the infrastructure and working environment of a health care facility that was first built nearly a century ago is bound to lead to an adjustment period. But centralized control of key energy-consuming facility systems can sure make the adjustment period more palatable—especially if the return on investment can be quantified in the seven-figure range on an annual basis. This is exactly what happened when Humility of Mary Health Partners upgraded the eight-story, 1-million-square-foot St. Elizabeth Health Center in Youngstown, OH, earlier this decade. It has seen a $1 million-plus-per-year return on reduced energy costs, largely due to construction of a new cooling plant and a major refurbishment of the center’s onsite laundry and medical waste-disposal facilities.

The project won a 2006 Governor’s Award for Excellence in Energy from the Ohio Department of Development’s Office of Energy Efficiency (OEE), which was established as part of the Ohio Energy Strategy. The strategy mandates a competitive awards program to recognize companies, organizations, and individuals.

According to Wayne Tennant, vice president of facilities and construction for Humility of Mary Health Partners/St. Elizabeth, the reason for the upgrade was purely the fact that the center was antiquated and not as cost-efficient as possible given available new technologies. “The building ranges from the first section being built in 1912 with the second section being completed in 2002, but the majority of the building was built between that 1912 and 1970 time frame; that houses most of our patients—that’s the largest capacity we have,” he says. “We recognized there was a need to upgrade to try to gain some efficiencies and our costs associated with that rather than get into full-blown new construction.”

The most inefficient system in the facility was the cooling system, which like many in older facilities evolved in a piecemeal fashion with each addition to the building. The result was a decentralized infrastructure of cooling systems dedicated to each addition. Mark Giardini, a project manager for Siemens Building Technologies who worked on the entire facility upgrade, notes that the controls in this disparate cooling system were mainly pneumatic or older digital types of controls.

“We brought in a team to look at all aspects of their business and what we could do to improve on their current practices and ultimately save them money in the long run,” Giardini says. “So we went through a pretty extensive survey and developed about 25 different improvement measures that could fit their needs.”

Even though St. Elizabeth was not being reconstructed, the solution to the inefficient cooling was to construct an entirely new cooling plant, centralize the plant controls, replace air handlers with more efficient ones, and replace direct-expansion cooling coils with water coils, which in this instance were more efficient because chilled water was very inexpensive to produce with new chillers.

Three 1,200-ton centrifugal chillers and a variable-speed pumping system were installed in the 6,000-square-foot central cooling plant. The chillers are not only more efficient than the ones they replaced—most of which were at least 30 years old—but they also utilize variable frequency drives (VFDs) that run them at less than full capacity when the weather dictates, resulting in significant energy savings during the course of a year.

“By consolidating them into one location, we were able to stage our chillers,” Tennant says. “Depending on the temperatures, we can run one primary chiller or add on if the temperatures or humidities increase. That aspect was, I think, the big driving force: Getting them all together gave us the ability to do that as well as some redundancy in case we had one chiller fail us.”

Advertisement

A Siemens Apogee building automation system allows the facilities staff to monitor and control the new cooling plant. The automation system includes networked panels located in the building’s mechanical rooms that tie together air handlers throughout the facility. The networked panels send operating data to, and receive commands from, an Insight server. Software gives the hospital’s authorized users the ability to set temperature parameters for the new cooling system and monitor the operating conditions on any computer. Parameters can be set on equipment such as filters and thermostats to activate alarms when temperatures fall outside of the set parameters. The facilities staff can also view via a graphic user interface the operation of any equipment that is incorporated into the automation system. The ability to monitor all of this equipment from a central location saves the staff the time of walking the entire facility and physically checking the various systems’ components.

The combination of the automation system and the VFD-equipped chillers also allows the facility to reduce its energy costs, Tennant adds. “Our shoulder months are sometimes problematic, but our control system gives us the leverage to control that,” he says. “Having that central control gives us the ability to monitor our demand and achieve some efficiencies as far as comfort for our patients and also for the utility side of things.” Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!