July-August 2009

Data Centers and DG

IT facilities, which are making great strides in improving energy efficiency, are a natural fit for onsite power generation.

Article Tools

Create a Link to this Article

Photo:Sun Microsystems

Additional Article Content

By Don Talend

Comments


The equipment in an acquired 496,000–square foot lab and data center in Louisville was moved to Sun’s campus in nearby Broomfield, where overall IT equipment floor space was compressed to 126,000 square feet and 165,000 square feet of raised floor was condensed to 700 square feet, says Monroe. This reduction alone reduced much of the facility costs, because it eliminated the need for additional reinforcement to support the weight of the servers, which can weigh as much as 1 ton per rack, according to Monroe. Noting that raised floors have traditionally served dual purposes of facilitating the distribution of both chilled air and cabling, he says, “Unfortunately, those two purposes are at odds with each other because the more cabling you put underneath the floor, the more it restricts the airflow, and the more problems you have with the cooling system because the air becomes unbalanced—you have hot spots.”

The facility’s cooling system uses containment of hot air produced by the servers within the aisles. Another feature of the design, notes Monroe, is the close proximity of the cooling equipment to the IT equipment; in many cases, the hot air only travels 2 or 3 feet before being blown across cooling coils, and gets blown around to the front of the computer. The facility utilizes “close-coupled cooling” with Liebert Corp. overhead cooling systems and APC row-level cooling systems. The design and equipment are much more efficient than a traditional data center design that allows hot air to meander to a register all the way across the room before being blown under a raised floor, Monroe points out.

Additionally, the facility is equipped with two Trane variable-speed centrifugal 500-ton chillers with two-stage compressors that are 25% more efficient than American Society of Heating, Refrigerating, and Air-Conditioning Engineers standards. “We also use quite a bit of evaporative cooling; rather than run the chillers here in Colorado on a day when it’s 45°F and gets down to the twenties at night, we use a flat plate evaporator out in the cooling tower to do the heat exchange, and we can get over 1,000 hours of cooling each year,” says Monroe. The cooling system uses a Clearwater Dolphin closed-loop electromagnetic purification system for the chiller water that saves the facility about 675,000 gallons of water annually, according to Monroe.

Photo: NetApp
Powersmiths transformers are being used to increase energy efficiency at a new NetApp Inc. engineering and data center
.
The cabling in the facility also has been reconfigured according to Sun’s pod architecture, another design item that reduced costs, Monroe adds. The networking and power distribution cables are located above the server racks and power distribution equipment is now located above the server racks in what is described as a pod design. Power distribution boxes such as three-phase, 208-V or single-phase, 110-V can be twisted into an overhead Universal Electric Corp. Starline Plug-In Busway system, reducing the amount of copper wire needed by about half, according to Monroe. “With a raised floor, no one ever pulls cable out,” he says. “It’s either too long or too much work, so when modifications are made over the life of a data center, copper cable builds up underneath there in the form of networking cables and power cables. With this overhead system, every time we make a modification, we take the old cable out, we put the new cable in, and we’re going to save tons of copper inside the data center, which is a scarce resource these days.”

Another energy saver is the use of flywheel-based UPS rather than traditional lead acid batteries, Monroe points out. “Number one, they run more efficiently all the time, and number two, they don’t have this room full of lead acid batteries that need to be replaced every six years, meaning that you’ve got to dispose of the lead and chemicals,” he says. Monroe recalls a day in February 2009, when high winds caused a power outage but the flywheels started up the backup generators, which provided uninterrupted power for a couple of hours.

Advertisement

Advanced Data Centers
A multidisciplinary team engineering approach to improving energy efficiency resulted in a PUE that is pushing the limit of theoretical achievement for San Francisco, CA-based Advanced Data Centers’ first data center on the former McClellan Air Force Base near Sacramento, CA. The company will provide facility space and equipment for customers that opt to not operate their own data centers. By exhausting equipment-generated heat, making the distribution of chilled water more efficient, and other methods, the team is expected to obtain a PUE of 1.12 when the 200,000–square foot facility is completed in late 2009. The design is estimated to provide about $2 million in energy savings every year, a fact not lost on the Sacramento Municipal Utility District, which awarded the three-year-old startup with its largest-ever rebate under the “Savings by Design” energy efficiency incentive program.

Bob Seese, the company’s chief data center architect, says that the multidisciplinary team approach to facility design that came about in 2007 was a result of the movement toward energy efficiency in data centers. Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!