July-August 2009

Data Centers and DG

IT facilities, which are making great strides in improving energy efficiency, are a natural fit for onsite power generation.

Article Tools

Create a Link to this Article

Photo:Sun Microsystems

Additional Article Content

By Don Talend

Comments


“At that time, the industry, although it was starting to migrate in that direction, still thought that electric costs and the electricity that was being used by data centers were untouched areas because a data center had to remain operational 24 hours a day, seven days a week, and 365 days a year, and touching energy could, they felt, impact its reliability,” says Seese. “Understanding that that was the industry’s position, I had to support my position. I thought that there was a lot of opportunity for savings in terms of cooling.”

Seese put together a team of experts in multiple engineering disciplines including electrical, mechanical, and structural. Significantly, he adds, collaborations were based on the Rocky Mountain Institute’s charette concept. “We instructed everyone when they came to these charettes to leave their particular specialty at the door and, instead, come into the room and be an engineer that day—not necessarily a structural, civil, or mechanical engineer.”

He credits the approach as instrumental in helping the team to get the facility pre-certified for a US Green Building Council’s Leadership in Energy and Environmental Design Core and Shell Platinum rating.

Photo: NetApp
A vari-prime chilled-water distribution system is used in conjunction with these Trane chillers to efficiently cool the NetApp facility.
“They really did find creative solutions instead of just going back to the old habits of doing things the way they had always been done,” says Seese. “A lot of that was based on the naïveté of engineers, who maybe didn’t understand mechanical engineering, but they asked, ‘Why don’t you do it this way?’ And in a lot of cases, the mechanical or electrical engineer would come back and say, ‘Let me see if that solution does work.’”

One of the most important strategies that the team used, Seese points out, was making use of the outside air temperature in the Sacramento area. “We looked at the weather in the Sacramento area and found out that we could use outside air to cool our facility 75% of the year,” he says. “In a typical data center, chillers consume as much as 0.6 kW per ton—that’s a lot of energy. If we could find a way to use outside air and not cause problems with the dust count in the air, we could save a lot of energy.”

Seese adds that Rumsey Engineers of Oakland, CA, which had assisted in the design of many “clean rooms” for semiconductor manufacturing, had successfully utilized outside air for cooling these facilities.

Advertisement

Average high temperatures in the Sacramento area range from 55–82°F between November and May, compared with 89–94°F from June through September. The bigger challenge in bringing outside air into the new facility via high-efficiency fans, Seese says, was controlling the humidity for a few days out of the cooler months—without consuming a lot of power. Noting that the region usually has optimal humidity for the natural cooling strategy, he reports that high-efficiency atomizing dehumidifiers will be used to dehumidify the return air stream.

During months in which it was necessary to chill water for cooling, the facility will use up to six modular centrifugal chillers: five 750-ton units and a 250-ton unit for low-load conditions for initial occupation of the space. The 250-ton unit and one of the 750-ton units are equipped with variable frequency drives; Seese explains that these two units would be used in situations where 850–1,500 tons of chilled water are needed, and the other 750-ton units can be utilized incrementally when more than 1,000 tons are needed. Another significant cost-saving aspect of the facility, Seese adds, is the fact that the chillers are located outside of the facility. “We had to put our chillers outdoors because putting our chillers indoors would have had too much of an impact on the amount of real estate we had to lease out for business purposes—we had a certain number of square feet to rent,” he notes. “They don’t like the rain, so you have to cover them; this solution puts the cooling towers over the top of the chillers.” Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!