July-August 2009

Medical Power Practices

Case studies in standby emergency power

Article Tools

Create a Link to this Article

Photo: @iStockphoto.com/Maksymka

By Lori Lovely

1 Comments


Switching—and Sharing—Gear
The collaboration of Vanderbilt, Smith, Seckman & Reid and a local Caterpillar dealer concluded in The Vanderbilt Clinic Highbay Power Plant project in 2006. Things moved quickly, with a presentation in June, followed by coordination in July, and design the following month.

“We spent about six months on design and one year on construction,” reports Ross.

Equipment packages were purchased in November and December 2006 for the $6 million project—a budget increased from the original $4–5 million. “We proposed a 9-MW plant in the Highbay area or parking deck across from hospital,” he explains.

Despite the fact that the anticipated load for the existing hospital, clinic, and new tower could be served with a 6-MW plant, additional capacity was planned for future consolidation of smaller, individual generators on campus.

Vanderbilt wanted “n+1” capacity for the new plant, where the code required essential load is “n” and the “1” is a spare generator. Ross explains, “The n+1 design philosophy was important to hospital maintenance, because they can have a generator down for maintenance and know they always have enough capacity to serve the code-required essential loads.”

The team agreed to use the spare generator to run a chiller in the new tower basement when it wasn’t required for essential loads. The generators were designed for 4160 V to reduce the distribution costs from the new plant and to be able to serve the 4160-V chiller.

Photos: John Ross
The collaboration concluded in The Vanderbilt Clinic Highbay Power Plant project in 2006.

The hospital received the newer generators, while its three 1,200-kW generators were relocated to the Medical Research Building, which required no additional capacity.

Although the new tower Ross was working on was integrated into the hospital, they had to add separate generators because it was not integrated. “We didn’t need all that space for the tower, so we used it for generators for the hospital,” he says. “That left for enough space to eliminate extra gen.”

The final plan to provide reliable redundant standby power with automatic switchover capability during power interruptions required four Cat 3512B 1,500-kW generator sets with customized switchgear. According to a Caterpillar publication, “Each Cat generator set produces 4,160 volts for transmission to 480-volt substations.” The new components were designed to use 15-kV breakers, matching the existing wiring at Vanderbilt. Not only did that integrate the new system better, but it also improved the versatility of power distribution.

Ross explains that because the majority of Vanderbilt’s equipment was already Cat, there was a strong desire to go with Cat gensets. Besides, he notes, their pricing was better. Although all hospital transfer switches were Russelectric, Caterpillar proposed their ISO paralleling gear as a packaged solution for the plant. Vanderbilt chose to go with the Caterpillar solution for this project.

With the addition of the new building, the hospital’s emergency branch loads totaled more than one 1.5-MW generator. Per the National Electric Code, power for the emergency branch loads has to be available within 10 seconds. “We couldn’t guarantee that one generator would be online and a second paralleled and closed in within 10 seconds, so we designed the switchgear with two separate paralleling buses with equal generators connected, and divided the emergency branch distribution between the busses,” says Ross. “A tie breaker was designed to allow the two busses to be synchronized together after all generators were connected to their respective busses, so the system operates as a single paralleled system once it is running.”

Photo: Eaton Corporation
The double-ended parallel switchgear with parallel ties across the break allows each bus to come online within the mandated 10 seconds, so that the total emergency branch load is powered within the code required time, then synchronized. It’s not unique, he adds, but it is one way to meet the code requirement for emergency power for essential systems.

Advertisement

The metal-clad switchgear with Powerlynx 3000 control, enhanced operator interface with touch-screen controls and remote PCs for monitoring and control allow tracking of power output and distribution, as well as routine maintenance, in real time from a remote PC. The switchgear is compatible with the existing Automatic Transfer Switch interface and is used during mandated testing to simulate a power supply shutdown and switch over to full output within the required 10 seconds.

By taking the entire hospital and clinic emergency load onto the new generator plant, not only did they ensure that the hospital had reliability in the new emergency plant with added capacity for chillers when necessary, but they freed up the older hospital generators for use at the Medical Research Building (MRB). “The old hospital generators are serving the MRB,” elaborates Ross. Next Page >

What Do You Think?

Post a Comment

jobigger

July 2nd, 2009 7:47 AM PT

I have been a reader/subscriber of Distributed Energy since Issue No. 1 and look forward to each issue. That said, I found the author's descriptions in "Medical Power Practices" of the equipment and systems for Vanderbilt University's Medical Center emergency power system to be very confusing. A large portion of the word descriptions in the article could have been replaced by simplified one-line diagrams of the hospital campus systems, for instance. And what cost and performance information that was provided was sprinkled throughout the article; a concise summary is much more valuable to the reader (see, for example, Table 1 on page 20 of this issue). The Caterpiller units are impressive but one or two of the photos could have been replaced with other graphics that would increase the reader's understanding of the overall system's operation and benefits. Connecting together various emergency and alternative electric generating systems to create high-efficiency, -reliability, or -security networks on a university campus, medical complex, or industry development is being recognized as an opportunity for significant savings of energy and funds. Clarity is critical to describing these projects. For a comparison, an article appeared in the April 2009, issue of POWER magazine (page 22) describing a similar project to increase reliability of the Illinois Institute of Technology campus in Chicago, Illinois.

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!