May-June 2005

  • 1
  • 2

Ontario Energy Management Project Temporary PowerFast

On August 14, 2003, the largest electrical blackout ever struck North America. Where are we now?

Article Tools

Create a Link to this Article

By Peter Hildebrandt

Comments

Occuring less than two years after the September 11th attacks, the August 14, 2003, blackout “again pointed out our vulnerability, ” says Neil Karr, head of project management for ALSTOM Power Rentals (APR). Much of the entire region of Ontario was hit, along with much of the Eastern Seaboard of the US and Canada.

“During the blackout,” Karr continues “our generator units at the Ontario Energy Management project site ran for three days as the main power grid steadily came back online.” Thus APR’s Ontario Energy Management project was able to do exactly what it was meant to do—be part of a system that could supply peaking power during a time of high demand for power.

Project Background and Rationale
In April 2003, the local utility in southern Ontario started looking for a significant amount of additional power generation—200 MW of power or more. The power was to be distributed around much of that region of Ontario. The reason for the project was simply to provide additional power during periods of peak electricity usage. “It was really installed as a security measure, or an insurance policy,” says Paul Marcroft, business development manager for APR, “and to support the existing infrastructure system during the peak periods.”

To fulfill this need, Ontario Energy Management Inc. (OEM) and APR were awarded a temporary power contract for Ontario, Canada, for 20 MW. The customer, Ontario Electricity Financial Corporation (OEFC), decided that the Transportable Tempest gas turbine generating system could contribute to solving their problem.

One other factor may have been that the elections were coming up in a short while. “I think, perhaps, the government wanted to make sure that they didn’t have any lights out during this election period,” suggests Marcroft, “that is my opinion, perhaps, rather than the facts. But whatever the case, they wanted extra power to meet demands during the peaks—whether it was political or not.”

“It was to prevent rolling blackouts,” adds Christopher L. Hobbs, project engineer with Peninsula Engineering and Ontario Energy Management. “When the whole Eastern Seaboard was hit by the blackout last August 2003, we were able to run through the entire period. ALSTOM Power Rentals did a very good job for us through the entire project. Almost all the details of setting up their project were very much cookie cutter in nature. The engines arrived July 24th and on August 1st we were putting full power into the grid. The total time involved was one week.” Says Hobbs, “If that’s not unusual, then there’s not anything unusual out there. That is extraordinary. I challenge anybody, using as many hours in the day they want, to meet my week.”

There were other proponents selected during the bidding process. “They were all awarded with a contract,” says Hobbs, “but for a variety of reasons, timing or whatever, they could not deliver. Only three of these actually delivered. We were one of the three. The other two proponents were multibillion-dollar-per-year companies, Caterpillar and Trans-Canada Pipeline.”

The decision to proceed with the project was made on June 6, 2003, by the Canadian government. “Ontario Energy Management did have some hiccups along the way,” says Hobbs, “but fortunately none of them had anything to do with ALSTOM.”

When asked if there were any lessons to be learned from this project, Hobbs says, “I can’t think of anything in particular. It was a lot of work to put those things in for such a short duration. But then again, those units really are designed to be mobile and easily connectable. That it all worked out so well was certainly a pleasant surprise for us.”

“The government’s expectation was to put in temporary power generation, which would allow them to make it through their peak generation periods,” says Karr, “This was in the event that they lost one of their own units or in the event that demand went too high. So what they ended up doing was putting in several sites with generation capabilities. In the blackout these enabled everybody to go online.”

Advertisement

The APR equipment didn’t actually run much at all. It just sat there for the six months of the contract in anticipation of a problem. So it was strictly a peaking plant. “But the fact of the matter was,” says Paul Marcroft, “it was never really run very much because the high peaks never materialized.”

“It was not a single-source setup,” says Marcroft, “there were a number of different authorized generators in the area that were successful in winning part of the project. There were also several different technologies being applied and ALSTOM was fortunate enough to get 20 megawatts.” Next Page >

  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!